Thursday, May 9, 2019

CBPOA - May 1st, 2019, General Meeting Minutes


Directors Present: Andrew, Jim, Bruce, Robert, Derrick.                                                Alexandra Neighborhood House

1)      Call to order at 7:33 PM

 Andrew welcomed Councillor Linda Annis and the over 60 members in attendance.

2)      Presentations:  2:1) Tindi Sekhon, City of Surrey, gave a presentation on the Drainage and Paving Project.

More complex archeological work delayed last year’s Phase 1 completion into 2019. This work is expected to be completed by the end of the month with some restoration work still be carried out. Phase 1 came in at triple the expected cost through the additional archeological work - a lot of tools were found and some baskets, preserved in a clay layer.  Phase 2 will concentrate on underground costs.

The 2019 Phase 2 work will start in late June and is scheduled to take four months, depending on the archeology uncovered. There had to be a change in the archeological consultant so there have been some permit delays accounting for the later start.

The phase 2 work will utilize the same contractor as last year and those affected last year were happy with the contractor’s performance.  The work will start on McBride and work Sullivan to Target to Wickson.  Then work O’Hara Lane.

It is recognized that the work will be occurring in peak season, traffic control must be effective and the contractor is aware of O’Hara Lane being used by children on bicycles in July and August. Most likely the O’Hara work will be September time.

On O’Hara, unlike the other streets, the final road surface will have a slight dip to the road centre, like a reverse crown.  Excavation through tree root zones will be by hydro-vac with an arborist on site and two trees will be removed. A nest survey will be carried out. It is recognized that this is a tight location and any excavated material requiring to be sieved will be moved out. Garbage trucks may have to back up and the contractor will help with the bins.

In answer to questions Tindi will talk to the contractor about surface puddles and directing visitor traffic.

Tindi stated that he will make a map available; he is happy to meet with residents and has provided his e-mail address if anyone has detailed questions.  THSekhon@surrey.ca
The members thanked Tindi with a round of applause.

                                    2:2) Greame Cross, City of Surrey, Fence and Whistle Cessation.

Graeme outlined the history of the pursuit of whistle cessation and that City staff have been persistent for quite some time.

2012 – Surrey hired a consultant to carry out a safety assessment for the rail crossings and this was discussed with BNSF.
2012/13 no resolution/ agreement
2014 – The Federal Government passed new rail crossings regulations and standards and a whistle cessation procedure. This requires an agreement be reached between the Rail Company and the Local Authority, following which the Local Authority issues an order and the Rail Company has 30 days to comply.
2015 – Another safety assessment, under the new regulations, was carried out. BNSF told Surrey they had concerns about pedestrian trespass and a fence along the line would be required.
2016 – A conceptual alignment for the fence was developed and many enquiries from Surrey to BNSF with little or no response back. Long e-mail chains from Surrey, no action from BNSF.
Feb 2017 – Four follow-ups from Surrey – the fence jogged along the City/Railway property line and BNSF brought up the topic of a lease payment for the fence placement.
2017 – had an in-field meeting with BNSF and they said they required an annual lease of $225K.
Feb 2018 – BNSF remain resolute on the amount of the lease cost so let’s forget about trying to install a fence on rail property and install it on the City side of the property line.
May 2018 – Bayview residents raise concerns about loss of parking and driveway access issues so needed to do more consulting to try to reach a compromise.
2018 – Transport Canada to provide cost sharing of $122K for the fence and crossings.
Looking in more detail in the zone where a fence could potentially be installed on City property.
Nov 2018 meet with BNSF at City Hall. The annual lease amount ask has been substantially reduced to an acceptable figure and have a verbal agreement with BNSF that they will prepare a lease that allows the fence to be located on BNSF property. Walked the line again with BNSF for clarity on the fence alignment and BNSF, for rail safety, now requires the fence to extend further south than the end of Bayview, to the steep bank and their slope detection cable system.
Jan 2019 – Surrey provides another line drawing of the fence alignment.
2019 Jan to May – repeated requests made to BNSF about when the lease will be forthcoming. No responses received. Took a more detailed look at where the fence could potentially be placed on City property – found serious issues with underground utilities in the fence location zone – two large dia. Vancouver managed sanitary mains, a large storm water pipe and a Fortis gas main.

Current situation: the Federal funding ended on the April 1st year end; funds do not carry over from year to year. Will have to reapply.
Unable to obtain a lease document from BNSF or even a response as to when a lease document might be available.
Limited opportunity to place the fence on Surrey property because of underground utilities.
There is a meeting scheduled within the City to consider what might be done to pressure BNSF to respond. This, in the context of the rail speed boundary extension to the south and continuing issues with the slope stability of the escarpment.  What role can Transport Canada play towards gaining resolutions to these issues?

There followed an active question and discussion session, including what technologies, beyond the 100 year old whistles and horns, might be employed to further rail safety and whistle cessation.

As discussed, for those who want to offer their ideas and/or frustrations directly, they should send an e-mail to the Federal and Provincial Ministers of Transportation.
The e-mail should cc our local Federal MP and Provincial MLA, who are:
MP: Gordie.Hogg.A1@parl.gc.ca       MLA: T.Redies@leg.bc.ca   
             The members thanked Graeme with a round of applause.

Given that the time was now 8:45 PM, the President called a short break. Many members left the meeting.

Continuing with the circulated genda:

3)      Neighborhood Concept Plan for Crescent Beach, (NCP), – is this something the membership wish the Directors to pursue with the City? Deferred to a future meeting.

4)      Adoption of the March 6th, 2019 General Meeting draft Minutes. Proposed: Jim, Seconded: Dave.  All in favor.

5)      Matters arising from the minutes:   None.


No comments: